Site icon 99.1 FM CKXS | Your Music Variety

Murray Street Bridge To Be Closed This Week

Murray Street Bridge, Wallaceburg.

Commuters in Wallaceburg are in for more traffic headaches this week with the closure of one of the town’s main bridges.

Chatham-Kent’s engineering department will be closing the Murray Street Bridge daily between 8 a.m. and 4 p.m. beginning Tuesday. The closures will run through Friday.

The span over the Sydenham River will reopen each night from 4 p.m. until 8 a.m.

During the closures, the municipality will conduct final testing and commissioning of the bridge’s new sensors.

The upgrades to the bridge are part of a $1.9 million rehabilitation project, which also included upgrades to the steel bridge deck, various concrete repairs, and improvements to the lift mechanisms/infrastructure. The majority of the work was completed between March 8 and April 30. The project is expected to be completed in its entirety before the end of the year.

Exit mobile version